REQ-1042 · Northgate Logistics Center · HVAC Equipment & Installation
Confirm RTU-3 curb height with revised roof assembly
Raised by Dana Whitfield (Evans General Contractors) on 2026-08-18
The roof assembly changed to a 4" tapered insulation package in ASI-07. Please confirm the RTU-3 curb height still nets a level equipment base, and advise if an extended curb is required before fabrication release.
Awaiting a response from Ron Borden.
Extended curbs add roughly two weeks to the build slot — flagging that now so the schedule reflects it if needed.
Dana Whitfield
Requester · Evans General Contractors
Ron Borden
Responder · Apex Mechanical Systems
Bill Hollis
Watcher · Thermaline Equipment Co.
Created request
Dana Whitfield · 2026-08-18 09:12
Assigned to Ron Borden
Added as watcher
Bill Hollis · 2026-08-19 14:40
ASI-07-Roof-Assembly.pdf
1.8 MB · Dana Whitfield · 2026-08-18