REQ-1042 · Northgate Logistics Center · HVAC Equipment & Installation

Confirm RTU-3 curb height with revised roof assembly

RequestOpenHighDue 2026-08-26Ball in court: Ron Borden
Description

Raised by Dana Whitfield (Evans General Contractors) on 2026-08-18

The roof assembly changed to a 4" tapered insulation package in ASI-07. Please confirm the RTU-3 curb height still nets a level equipment base, and advise if an extended curb is required before fabrication release.

Response

Awaiting a response from Ron Borden.

Comments
Bill HollisThermaline Equipment Co.2026-08-19 15:02

Extended curbs add roughly two weeks to the build slot — flagging that now so the schedule reflects it if needed.

Participants

Dana Whitfield

Requester · Evans General Contractors

Ron Borden

Responder · Apex Mechanical Systems

Bill Hollis

Watcher · Thermaline Equipment Co.

Status History

Created request

Dana Whitfield · 2026-08-18 09:12

Assigned to Ron Borden

Added as watcher

Bill Hollis · 2026-08-19 14:40

Attachments

ASI-07-Roof-Assembly.pdf

1.8 MB · Dana Whitfield · 2026-08-18