Northgate Logistics Center · PKG-118-23

HVAC Equipment & Installation

Six packaged rooftop units, associated curbs, ductwork fabrication and installation, and warehouse ventilation fans for Building A.

Package Health

At Risk

At risk: RTU-3 submittal comments outstanding and the released fabrication date is inside the float window.

Current Stage

8 of 14

Submittal Approval

Next Milestone

Rooftop unit submittal approval

Target 2026-09-04

Contract Value

$2,415,000

3 open · 1 overdue items

14-Stage Package Journey
CompleteIn ProgressBlockedNot RequiredNot Started
Stage 8

Submittal Approval

In Progress
Stage Owner
Evans Project Team
Completed
Due
2026-09-04

RTU-3 selection comments pending resolution.

Package Team Directory

Contact visibility is granted per package assignment — some contacts are reachable only through the portal.

Evans Project Team

3
DW

Dana Whitfield

Senior Project Manager

Evans General Contractors

Package Owner
TR

Tomas Reyes

Superintendent

Evans General Contractors

Site Coordination
PN

Patrice Nolan

Project Engineer

Evans General Contractors

Submittal Review

Direct contact not shared for this package

Manufacturer / Supplier

2
BH

Bill Hollis

Regional Sales Manager

Thermaline Equipment Co.

Equipment Supplier
GY

Grace Yuen

Applications Engineer

Thermaline Equipment Co.

Technical Support

Direct contact not shared for this package

Installing Contractor

3
RB

Ron Borden

Project Manager

Apex Mechanical Systems

Installation Lead
SP

Shawna Pike

Field Superintendent

Apex Mechanical Systems

Field Supervision
DC

Dell Cruz

Foreman

Apex Mechanical Systems

Crew Lead

Direct contact not shared for this package

Designer

1
IF

Imani Foster, PE

Mechanical Engineer of Record

Lowcountry Design Group

Design Review

Commissioning Agent

1
GS

Greg Sandoval

Commissioning Authority

VerifyBuild Commissioning

Cx Agent

Direct contact not shared for this package