Northgate Logistics Center · PKG-118-23
HVAC Equipment & Installation
Six packaged rooftop units, associated curbs, ductwork fabrication and installation, and warehouse ventilation fans for Building A.
Package Health
At risk: RTU-3 submittal comments outstanding and the released fabrication date is inside the float window.
Current Stage
Submittal Approval
Next Milestone
Target 2026-09-04
Contract Value
3 open · 1 overdue items
Submittal Approval
In Progress- Stage Owner
- Evans Project Team
- Completed
- —
- Due
- 2026-09-04
RTU-3 selection comments pending resolution.
Contact visibility is granted per package assignment — some contacts are reachable only through the portal.
Evans Project Team
3Dana Whitfield
Senior Project Manager
Evans General Contractors
Package OwnerPatrice Nolan
Project Engineer
Evans General Contractors
Submittal ReviewDirect contact not shared for this package
Manufacturer / Supplier
2Bill Hollis
Regional Sales Manager
Thermaline Equipment Co.
Equipment SupplierGrace Yuen
Applications Engineer
Thermaline Equipment Co.
Technical SupportDirect contact not shared for this package
Installing Contractor
3Ron Borden
Project Manager
Apex Mechanical Systems
Installation LeadShawna Pike
Field Superintendent
Apex Mechanical Systems
Field SupervisionDell Cruz
Foreman
Apex Mechanical Systems
Crew LeadDirect contact not shared for this package
Designer
1Imani Foster, PE
Mechanical Engineer of Record
Lowcountry Design Group
Design ReviewCommissioning Agent
1Greg Sandoval
Commissioning Authority
VerifyBuild Commissioning
Cx AgentDirect contact not shared for this package
Confirm RTU-3 curb height with revised roof assembly
REQ-1042 · Ball in court: Ron Borden
Ductwork routing conflict with sprinkler main at Grid F-6
ISS-1039 · Ball in court: Ron Borden
Provide startup technician certifications for RTU commissioning
ACT-1031 · Ball in court: Greg Sandoval
Damaged curb delivered for RTU-1
ISS-1019 · Ball in court: —
RTU Equipment Submittal — Rev 2
Submittal · Rev R2 · 2026-07-30
Ductwork Shop Drawings — Building A
Drawing · Rev R1 · 2026-07-18
Subcontract Agreement — PKG-118-23
Contract · Rev Executed · 2026-04-02
RTU-1 Curb Replacement Closeout Record
Closeout · Rev Final · 2026-07-10